GOOD ESTIMATING HABIT TO HAVE:
(this guide is focused on estimating Drywall,
Acoustic, Plaster, Painting and other Finish Trades)

1. Read the front-end bid documents first to get an
understanding of what is being required in the bid
proposal.

2. Review the Specifications thoroughly. Make list
of unusual job requirements, means, methods, and
materials gathered from the specifications. For
COLD FORMED METAL FRAMING, Engineered
shop drawings usually is being required. The wind
load and deflection criteria dictates GAUGE, SIZE,
AND TYPE OF FRAMING MATERIALS.

3. Scan drawings of the project to obtain a general
idea of the job and how the drawings are organized.
Visualize image or appearance of the project while
flipping through the drawings. Take note of critical
details and unusual detail conditions. Determine
deck heights, ceiling heights, number of floors, and
other pertinent information needed during the
takeoff process. Understand the nomenclatures
being used in the project bid documents.

4. Obtain a general idea of the trade scope of work.
Make list of work items that are not generally part
of of the trade however, are being requested to be
included in the bid proposal. Also take note of
unusual job conditions that have cost impact to
productivity.

5. Understand the logistical issues of the project, i.e.
– access to site, type of project, hoisting
requirement, material distribution and clean up and
many others job specific issues. Consider timing or
scheduling of weather sensitive work items that
may require heat and other weather protection.
These costs have to be included in the bid proposal
unless provided by others. Costs of accessing the
work have to be included – scaffolding, lifts, and
other equipment.

A good estimator should be able to visualize
d
different aspects of
the project after viewing and
digesting information on
the floor plans, reflected
ceiling plans and elevation drawings.
He/she should
be able to determine the required components and
processes of the different work items or aspects
involving the project from the plan details. From
there, a good
estimator should be able to build the
project in his mind while estimating costs. This is
the basis of good estimating.
If you're unable to do
the above, you are not cut for the job as estimator
and strongly advise you find another job or line of
work.






































THIS PAGE IS UPDATED PERIODICALLY!
SUGGESTED PRODUCTION RATES:

1. Cold formed metal framing (exterior wall
framing) – 20 sf/hr. Production rate includes
layout, top track, bottom track, and bridging. Add
for slide clips, flex track, double track and if
welding is required - this production rate is
dramatically reduced by at least 15%.
Exterior soffit framing  may be isolated in the
takeoff process so a different production rate can
be applied, usually lower than the exterior wall
framing.

2. Exterior sheathing (dens glass, gypsum
sheathing) – 40 sf/hr. Usually applied over the
exterior framing, productivity can be heavily
impacted and dependent on the method or type of
access - stationary scaffold, swing scaffold, boom
lift, scissor lift, etc.

3. Exterior vapor barrier (Tyvek or asphalt felt
paper) –120 sf/hr. Beware - there are new products
now being specified that are more expensive and
take more time to install. Read the specifications.

4. Thermal insulation (fiberglass) – 100 sf/hr.
Thoroughly read the specifications for some
expensive thermal insulation materials being
required. If the insulation is unfaced, is interior
vapor barrier being required? Is 6 mil polyetheylene
the minimum specified material or is there other
vapor barrier such as Griffolyn (more expensive)
being specified?

5. Hang gypsum board walls (top-out) – 35 sf/hr.
If topping out operation commences after overhead
MEP rough-ins were installed – the production rate
should be dramatically reduced by at least 25%.

6. Hang gypsum board wall
s (bottom) – 64 sf/hr.
This production rate seems to be conservative,
however considering leave outs, out of sequence
work, and other site conditions - historical data
shows for this to be averaged.

7. Hang high impact board – 48 sf/hr. Although this
board finishes like a regular board, the installation is
labor intensive compared to regular or firecode
gypsum board.

8. Tape and finish walls (level 4) – 60 sf/hr. Once
again, this production rate is average. This
operation is being impacted by out of sequence or
come back work. The Level 5 finish - usually
required for paint finish, historically is around 55
sf/hr production rate.

9.  Firetape walls – 100 sf/hr, impacted by the
amount of MEP items above the ceiling and
accessibility of  the work.






























THIS PAGE IS UPDATED PERIODICALLY!
Estimating
Copyright 1994-2004, Quality Interiors, Inc. Downloads are for personal use only, not for resale to others, and may not be reprinted in any form
without written permission from Quality Interiors, Inc.

DISCLAIMER: We hope whatever you find on this site is helpful, but be cautioned that it may not apply to your own situation, or be totally current at
any given time. Quality Interiors, Inc. and all of its current and past experts, sponsors, advertisers, agents, contractors and advisors disclaim all warranties
with regard to anything found anywhere on this website or sent from Quality Interiors, Inc. and its related sites, publications and companies. We also take no
responsibility for comments published by others on these pages.

TRADEMARKS:  Quality Interiors, Inc.™.
East Side Location:

6645 E 38th St
Indianapolis, IN 46226
Tel: 317-713-7050
Fax: 317-713-7055
South Side Location:

3704 E Edgewood Ave
Indianapolis, IN 46227
Tel: 317-791-9486
Fax: 317-791-9536
Contact us at:

For Estimating:

East Side Location:
6645 E 38th St
Indianapolis, IN 46226

Tel. Number: (317)713-7057
Fax Number: (317)713-7055

South location:
Office/Warehouse:
3704 E. Edgewood Ave
Indianapolis, IN 46227
Tel. Number: (317) 791-9486
Fax Number: (317) 791-9536


e-mail address:
Basil Delacruz -
bdelacruz@qiico.com